Piping Walkdown Checklist

A piping walkdown checklist is used in industrial construction to assist the inspector in verifying that piping systems are built and installed correctly. The checklist functions as a to-do list, and ensures a thorough walkdown of all aspects of the piping system per written procedures and best practices.

What is the Purpose of a Walkdown?

The piping walkdown involves physically inspecting all aspects of the piping system while walking along it on-site to ensure all components, connections, and configurations align with the approved piping and instrumentation diagrams (P&IDs), isometric drawings, and project specifications.

A proper walkdown helps to find and correct issues with the piping system before operation and helps multiple departments accomplish the following objectives:

  • Quality: Ensures the piping system meets design and regulatory requirements.

  • Safety: Identifies potential hazards or installation errors before system commissioning.

  • Commissioning: Confirms the system is ready to be commissioned and put into service.

  • Documentation: Provides a record of inspection for project handover and future audits.

Pre & Post Pressure Testing Walkdowns

There are certain activities that cannot be completed until the pressure testing of a piping system is complete. Furthermore there are some activities that have to be done so that a piping system is ready to be properly pressure tested. As a result a Pre-Test and a Post-Test walkdown need to occur.

The following sections are key components of a Piping Walkdown Checklist…

General / Header

  • Header Fields: Document Title, company logo, document number, doc control features, page numbers, etc…

  • Common fields: Project Name, Project Number, Location, Jobsite, Date of inspection, System, Fluid, Line Number, PO Number, Owner, Unit/Building.

  • Include fields for reference documents: P&ID No., Isometric Drawings, Specifications.

Piping Installation

  • Piping installation matches isometric drawing & P&ID

  • Piping routing, alignment, orientation, and elevations

  • Pipe material, size, wall thickness match isometric drawing bill of materials (BOM)

  • Slope in piping and/or drainage lines are installed properly as required

  • Checking piping alignment between connections, especially as it attaches at equipment

Pipe Supports

  • Pipe supports, hangers, spring cans, anchors, guides, wear pads, etc. are installed correctly

  • Adequate support and proper spacing of supports per drawing

  • Supports and guides are properly installed to allow for the designed thermal expansion and contraction

Welding

  • Visual inspection of welds performed as required, before and during walkdown

  • Welding documentation shows that approved welding procedures were used

  • The correct preheats and filler metals were used for the welding, per the approved WPS

  • Review and verification of required NDE/NDT with the NDR reports included in package

  • Welding documentation is included in the package as required

Bolting

  • Correct material, size and rating of gaskets, seated properly

  • Correct bolt/stud, length, material, and diameter

  • Proper lubrication of bolting assembly per manufacturer or owner specifications

  • Alignment of flanges are within tolerance

  • Proper tightening sequence and torque was applied per requirements

  • Bolting documentation (Torque sheet) is included in the package as required

Fittings & Components

  • Fittings, flanges, elbows, tees, eccentric & concentric reducers installed correctly

  • Proper rating and/or schedule of installed fittings and components

  • Inspect flange face integrity on exposed surfaces not already bolted up

Valves

  • Flow direction is verified

  • Valve type, size, orientation, and proper operability confirmed

  • Valve tags exist and are checked for correctness

  • Confirm the correct valve trim per the isometric drawing

Instrumentation

  • Instrumentation is properly installed and tightened

  • Correct tagging or permanent labeling of instrumentation

  • Proper installation of vents, drains, and sample points verified

Cleanliness

  • Confirm the piping system is free of debris, dirt, or foreign materials

  • If special cleaning requirements exist such as internal blasting, or chemical cleaning ensure that those methods were completed, including internal visual inspection using white light or black light was required

  • External chemical cleaning such as passivation or pickling is complete if required

  • Air blowing or water flushing completed as required

Pressure Testing

  • Welding and NDE are complete

  • If required welds are not coated for pressure testing

  • Pressure sensitive valves or instrumentation are removed for testing

  • Correct pressure testing medium is used (Water/Hydro or Air/Pneumatic

  • Required testing pressure was achieved for the necessary duration

  • Calibrated test gauges were used during the test

  • Proper flushing and drying occured post test

Reinstatement

  • Temporary components related to pressure testing are removed

  • Pressure sensitive valves, components, or equipment removed or not installed before testing are installed

  • Pressure testing blind are removed, and flanges bolted up

  • Vents and drains are properly plugged or closed as required, sometimes including seal welding and NDE

Coating

  • Proper material preparation was performed to ensure adhesion of coating system

  • Proper coating system used on piping

  • Proper DFT dry film thickness of each layer, and the finished coating system is acceptable

  • Proper color per drawing or specification requirements

  • Complete coverage is verified, visually or by holiday/pinhole testing

Tracing

  • The correct electrical heat tracing or steam tracing is installed

  • The tracing system is properly installed and attached by the correct fasteners

  • Installation of tracing has not damaged the coating system

Insulation

  • Insulation is of the correct material

  • Insulation thickness is per drawings or specifications

  • Insulation coverage is complete

Punch List

  • Incomplete or incorrect items are placed on the walkdown punch list

  • Punch List items are often ranked by severity and at which phase of the process that they have to be resolved by.

    • Pre-hydro or before Pressure Testing

    • Pre-Commissioning

    • Pre-Operation

Next
Next

B31.3 Closure Welds